U-21986

A selected-source collection. The timeline runs oldest dated source first; the full source library runs newest first. It may include party statements and reporting as well as filings; each source is labeled.

Case at a glance

Locality / coverage
Indiana Michigan Power large-load tariff, not DTE’s project-specific contracts. [Michigan Public Service Commission source note]
Companies / parties
Indiana Michigan Power; MPSC official summary. [Michigan Public Service Commission source note]
Docket
U-21986 [Michigan Public Service Commission source note]
Scope
Large-load tariff amendments and a future rate proposal; current tariff sheets and later outcomes are not established here. [Michigan Public Service Commission source note]

Based on the dated selected sources below. Not a current approval or permit certification.

This is not a mirror of the full live docket. Search the official E-Dockets portal ↗

Context & decision pathway

U-21986 concerns Indiana Michigan Power's large-load tariff, not DTE's project-specific contracts. The August 27 MPSC release describes amended requirements for customers drawing at least 50 MW and a direction to propose a standalone large-load rate in the next general rate case. [Michigan Public Service Commission source note]

Known from these sources

  • The Commission's summary describes longer contract terms, minimum billing requirements and additional collateral. It is an official description of tariff amendments, not a verified current tariff sheet. [Michigan Public Service Commission source note]

Source-linked timeline

Oldest original source first. These are source publication dates, not dates of this page's publication or a new verification of today's status. Each source retains its documentary limits.

  1. · Michigan Public Service Commission

    U-21986: MPSC approves amended I&M large-load tariff

    Source details — U-21986: MPSC approves amended I&M large-load tariff

    The MPSC’s August 27 release says it approved amendments to Indiana Michigan Power’s tariff for customers drawing at least 50 MW, including longer contract terms, minimum billing requirements and additional collateral. It also directs I&M to propose a standalone large-load rate in its next general rate case. This is the Commission’s decision summary, not the controlling order or a verified current tariff sheet.

    Documentary status: Official decision summary — not an order · Original source ↗

Not established by this collection

  • The current tariff sheets, full controlling order and outcome of any later general rate case are not established by this source selection.
  • A requirement to propose a future rate does not establish that the future rate has been adopted or what every customer's bill will be.

Full source library · selected records

Selected source notes

All 1 selected source notes remain below, newest dated record first. Search, filter or save a note to drill further into the underlying sources.

1 recordSource date · newest first
MPSC record

U-21986: MPSC approves amended I&M large-load tariff

The MPSC’s August 27 release says it approved amendments to Indiana Michigan Power’s tariff for customers drawing at least 50 MW, including longer contract terms, minimum billing requirements and additional collateral. It also directs I&M to propose a standalone large-load rate in its next general rate case. This is the Commission’s decision summary, not the controlling order or a verified current tariff sheet.

Official decision summary — not an order