POWER. POLICY. PLACE.

Large-load contract review

Google / DTE proposal

Selected public-source material concerning the Google/DTE proposal in U-22058. Recommendations are not regulatory decisions.

Project at a glance

Locality / coverage
Van Buren Township, as identified in the Attorney General’s release. [Michigan Attorney General source note]
Companies / parties
Google / DTE proposal; Attorney General recommendations are attributable to that office. [Michigan Attorney General source note]
Docket
U-22058 — Google / DTE contract review. [Michigan Attorney General source note]
Scope
Ratepayer safeguards and reported conditional approval; the report is not the controlling order. [Planet Detroit source note]

Based on the dated selected sources below. Not a current approval or permit certification.

Selected source file. These records are not a current construction, financing, zoning or permit certification. Read the status and date of each source before relying on a claim.

Context & decision pathway

The selected Google/DTE source concerns proposed power contracts for a Van Buren Township data center in U-22058. It describes the Attorney General's recommendations about minimum monthly charges, exit fees and cost tracking—not adopted contract conditions. [Michigan Attorney General source note]

The decision pathway separates an intervenor's recommendations from a reported regulatory decision. An already-published October 1 Planet Detroit note reports conditional approval of DTE's Google contracts; that report is not the controlling order and does not show which June recommendations were adopted. [Michigan Attorney General source note][Planet Detroit source note]

Known from these sources

  • The Attorney General's June 11 release reports testimony seeking stronger ratepayer safeguards in U-22058. The recommendations are attributable to that office. [Michigan Attorney General source note]
  • Planet Detroit reported conditional approval on October 1. This is newspaper reporting, not the controlling order or an independent verification of every enforceable term. [Planet Detroit source note]

Source-linked timeline

Oldest original source first. These are source publication dates, not dates of this page's publication or a new verification of today's status. Each source retains its documentary limits.

  1. · Michigan Attorney General

    Nessel seeks stronger safeguards in Google power-contract case

    Source details — Nessel seeks stronger safeguards in Google power-contract case

    The Attorney General’s June 11 release says her office filed testimony in U-22058 concerning DTE’s proposed contracts for Google’s Van Buren Township data center. Her recommendations include increasing minimum monthly charges and exit fees and tracking costs to protect other customers. These are an intervenor’s recommendations, not adopted requirements; a later Commission disposition was not verified.

    Documentary status: Filed testimony reported — recommendations, outcome unverified · Original source ↗

  2. · Planet Detroit

    Michigan regulators OK DTE contracts for Google data center

    Source details — Michigan regulators OK DTE contracts for Google data center

    Michigan's utility regulator voted unanimously Thursday to grant conditional approval for DTE Energy contracts to power Google's 1-gigawatt data center project in Van Buren Township.

    Documentary status: News report; conditional approval reported, not a controlling order · Original source ↗

  3. · Michigan Department of Attorney General — office press release

    Attorney General seeks rehearing of DTE–Google contract approval in U-22058

    Source details — Attorney General seeks rehearing of DTE–Google contract approval in U-22058

    Michigan Attorney General Dana Nessel’s office says she filed a petition for rehearing in MPSC case U-22058, challenging approval of DTE’s contracts to serve Google’s Van Buren Township data center. The office argues that evaluating costs and benefits across the full 20-year term leaves other customers exposed to cost shifting, and seeks annual reconciliation and stronger financial protections. These are the Attorney General’s arguments in an official office press release, not new commission findings or a decision granting rehearing.

    Documentary status: Official AG press release announcing rehearing petition; requested relief not decided in source · Original source ↗

Not established by this collection

  • The controlling order's full terms and which recommendations became enforceable are not established by this source selection. The October approval report is not a substitute for those documents.
  • Utility-contract review alone does not certify local land-use approval, tax incentives, permits or project completion.

Full source library · selected records

Selected source notes

All 3 selected source notes remain below, newest dated record first. Search, filter or save a note to drill further into the underlying sources.

3 recordsSource date · newest first
News

Attorney General seeks rehearing of DTE–Google contract approval in U-22058

Michigan Attorney General Dana Nessel’s office says she filed a petition for rehearing in MPSC case U-22058, challenging approval of DTE’s contracts to serve Google’s Van Buren Township data center. The office argues that evaluating costs and benefits across the full 20-year term leaves other customers exposed to cost shifting, and seeks annual reconciliation and stronger financial protections. These are the Attorney General’s arguments in an official office press release, not new commission findings or a decision granting rehearing.

Official AG press release announcing rehearing petition; requested relief not decided in source

News

Nessel seeks stronger safeguards in Google power-contract case

The Attorney General’s June 11 release says her office filed testimony in U-22058 concerning DTE’s proposed contracts for Google’s Van Buren Township data center. Her recommendations include increasing minimum monthly charges and exit fees and tracking costs to protect other customers. These are an intervenor’s recommendations, not adopted requirements; a later Commission disposition was not verified.

Filed testimony reported — recommendations, outcome unverified