POWER. POLICY. PLACE.

Permit request / no approval action

Inkster

WDIV’s October 19, 2026 report describes no council motion to approve a special land use permit and the developer’s stated plan not to proceed at that location. This was not a recorded vote rejecting the permit.

Project at a glance

Locality / coverage
Inkster — a proposed Southern Street warehouse conversion, identified in the selected WDIV report dated October 19, 2026. [WDIV / ClickOnDetroit — Noelle Friel; Mondrae Murphy, photojournalist source note]
Companies / parties
Robert Kato of Klever Technology Center LLC, identified as the developer by WDIV in the selected report dated October 19, 2026; his future plans are attributed statements. [WDIV / ClickOnDetroit — Noelle Friel; Mondrae Murphy, photojournalist source note]
Docket
No project-specific docket established here; WDIV describes a local special land use permit request without supplying a case number in this selected note. [WDIV / ClickOnDetroit — Noelle Friel; Mondrae Murphy, photojournalist source note]
Scope
The WDIV report dated October 19, 2026 describes no council motion to approve the permit, not a recorded vote rejecting it. The developer told WDIV he did not plan to appeal or pursue that location; subsequent action is not established here. [WDIV / ClickOnDetroit — Noelle Friel; Mondrae Murphy, photojournalist source note]

Based on the dated selected sources below. Not a current approval or permit certification.

Selected source file. These records are not a current construction, financing, zoning or permit certification. Read the status and date of each source before relying on a claim.

Full source library · selected records

Selected source notes

All 5 selected source notes remain below, newest dated record first. Search, filter or save a note to drill further into the underlying sources.

5 recordsSource date · newest first
Video

Data center project halted after residents voice opposition

Click On Detroit | Local 4 | WDIV states: The developer, Robert Kato of Klever Technology Center LLC, had applied for a special land use permit to convert a vacant 40,000-square-foot warehouse on Southern Street off Michigan Avenue into a data center. After hours of public comments from residents, no council member made a motion to approve the request.

Inkster denies special land use permit for data center

News

Inkster residents pack city hall to oppose data center — council declines to approve it

WDIV reports that no Inkster council member moved to approve a special land use permit for a proposed data center in a vacant 40,000-square-foot warehouse on Southern Street, despite a planning commission recommendation for conditional approval. Residents raised environmental, noise and light-pollution concerns at the crowded meeting. Developer Robert Kato of Klever Technology Center LLC told the station he did not plan to appeal or pursue the project at that location. The report describes a lack of council action, not a recorded vote rejecting the permit.

News report; council took no approval action, developer says project will not proceed at this location