Based on the dated selected sources below. Not a current approval or permit certification.
Selected source file. These records are not a current construction, financing, zoning or permit certification. Read the status and date of each source before relying on a claim.
The already-published October 2 Michigan Public note adds campaign discussion about local control and data-center policy at Saline. Candidates' positions are political statements, not permitting or contract decisions. [Michigan Public / MPRN source note]
The August 27 local report discusses a construction milestone, emergency-power procedures and proposed township rules. Its permit discussion is dated reporting, not a final permit certification. [The Sun Times News source note]
Source-linked timeline
Oldest original source first. These are source publication dates, not dates of this page's publication or a new verification of today's status. Each source retains its documentary limits.
Source details — U-21990: DTE’s original special-contract application
Direct filing dated October 31, 2025 requests expedited ex parte approval of primary-supply and energy-storage agreements with Green Chile Ventures. It documents what DTE requested, not what regulators ultimately approved.
Documentary status: Actual filing — historical application · Original source ↗
Source details — U-21990: conditional approval of Saline contracts
The MPSC’s December 2025 release describes conditional approval of DTE’s special contracts, including additional customer safeguards and a large-load tariff filing requirement. This is historical background and an official summary, not the order itself.
Documentary status: Official decision summary — historical · Original source ↗
Source details — Oracle posts Saline construction update
Oracle’s March 30 post says vertical construction is underway and describes financing and development as on schedule. This is the developer-side company’s claim, not an independent construction or financing audit.
Documentary status: Company claim — historical post · Original source ↗
Source details — Nessel challenges approval of Saline power contracts
The Attorney General says her August 6 appeal brief challenges the MPSC’s ex parte review and treatment of customer-cost protections. These are the appellant’s arguments; no appellate ruling was verified in this research.
Documentary status: Appeal arguments; outcome unverified · Original source ↗
Source details — Saline construction and local rules advance
The Sun Times News reports a construction milestone attributed to Related Digital, updated emergency-power procedures and proposed township rules. Its wastewater-permit discussion reflects the situation on August 27, not a verified final permit decision.
Source details — Governor's race hits Saline Township, site of massive data center project
Michigan's gubernatorial candidates John James and Jocelyn Benson discussed local control and data-center policy during campaign stops tied to the Saline Township project connected to OpenAI and Oracle.
Documentary status: News report; campaign positions, not enacted policy · Original source ↗
Source details — OpenAI, Oracle data center fines for trucks on dirt roads nearly reach six figures
MLive’s indexed October 17 headline reports that fines involving construction trucks using dirt roads at the OpenAI and Oracle data-center project are approaching six figures. The full article was inaccessible during intake. The precise total, payment status and enforcement details still require review of the original article before publication.
Documentary status: Headline-only candidate; full article review required · Original source ↗
Source details — Residents voice concerns over Saline data center at EGLE meeting
MLive’s search-indexed account describes residents raising concerns at an EGLE hearing about a proposed wastewater-discharge permit for the Saline Township data center. The report discusses monitoring and potential effects on the Saline River, alongside responses from EGLE and Related Digital. This note is based on indexed article text; the original page was inaccessible and its publication date could not be verified. The hearing is not evidence that a permit was granted.
Source details — As Data Centers Advance, Questions Over Costs and Oversight Grow
The Sun Times News reports on the Saline Township data center’s proposed sanitary-wastewater permit, an October 21 policy summit, Dingell’s environmental inquiries about the U-M–Los Alamos proposal and DTE’s planned gas-generation expansion. The article distinguishes the historic Textile Road dumpsite from the proposed computing-center property and attributes residents’ concerns, agency responses and developer or utility assurances. It notes that DTE’s proposed $6.4 billion generation investment has not been approved for recovery from residential customers; cost allocation remains a regulatory question.
Documentary status: News report; wastewater permit and generation-cost allocation remain under review · Original source ↗
Unreviewed source candidate. The Invisible Operator states: A township voted down a data center. The developer sued. Here is how the Saline Township, Michigan fight ended.
Documentary status: Summary of the "The Barn" project · Original source ↗
Source details — Data centre expansion in US a key midterm election issue
News24 states: News24 Washington Correspondent Jonathan Kearsley visited Michigan, where a data centre roughly the size of 10 MCGs is being developed, a project that is becoming a key issue for Michigan voters in the upcoming midterm battle.
Documentary status: A look at the Saline data center from the Australia · Original source ↗
Source details — If This AI Data Center Leaves Early, It Could Owe $2 Billion
The Cost Of AI states: Michigan's regulators approved, with conditions, DTE Electric's contract for a ~1.4 GW data center for Oracle and OpenAI in Saline Township (Dec 18, 2025, case U-21990). The data center pays for at least 80% of the power it signed up for, used or not, for at least 19 years. If it shuts down early, it owes up to 10 years of those payments, which DTE's filing puts at about $2.26 billion. Anything left over, DTE covers, not its other customers. That's an exit fee.
Documentary status: Overview on DTE power for the "The Barn" · Original source ↗
The Cost Of AI states: Michigan's regulators approved, with conditions, DTE Electric's contract for a ~1.4 GW data center for Oracle and OpenAI in Saline Township (Dec 18, 2025, case U-21990). The data center pays for at least 80% of the power it signed up for, used or not, for at least 19 years. If it shuts down early, it owes up to 10 years of those payments, which DTE's filing puts at about $2.26 billion. Anything left over, DTE covers, not its other customers. That's an exit fee.
News24 states: News24 Washington Correspondent Jonathan Kearsley visited Michigan, where a data centre roughly the size of 10 MCGs is being developed, a project that is becoming a key issue for Michigan voters in the upcoming midterm battle.
A look at the Saline data center from the Australia
Unreviewed source candidate. The Invisible Operator states: A township voted down a data center. The developer sued. Here is how the Saline Township, Michigan fight ended.
The Sun Times News reports on the Saline Township data center’s proposed sanitary-wastewater permit, an October 21 policy summit, Dingell’s environmental inquiries about the U-M–Los Alamos proposal and DTE’s planned gas-generation expansion. The article distinguishes the historic Textile Road dumpsite from the proposed computing-center property and attributes residents’ concerns, agency responses and developer or utility assurances. It notes that DTE’s proposed $6.4 billion generation investment has not been approved for recovery from residential customers; cost allocation remains a regulatory question.
News report; wastewater permit and generation-cost allocation remain under review
MLive’s search-indexed account describes residents raising concerns at an EGLE hearing about a proposed wastewater-discharge permit for the Saline Township data center. The report discusses monitoring and potential effects on the Saline River, alongside responses from EGLE and Related Digital. This note is based on indexed article text; the original page was inaccessible and its publication date could not be verified. The hearing is not evidence that a permit was granted.
MLive’s indexed October 17 headline reports that fines involving construction trucks using dirt roads at the OpenAI and Oracle data-center project are approaching six figures. The full article was inaccessible during intake. The precise total, payment status and enforcement details still require review of the original article before publication.
Headline-only candidate; full article review required
Michigan's gubernatorial candidates John James and Jocelyn Benson discussed local control and data-center policy during campaign stops tied to the Saline Township project connected to OpenAI and Oracle.
News report; campaign positions, not enacted policy
The Sun Times News reports a construction milestone attributed to Related Digital, updated emergency-power procedures and proposed township rules. Its wastewater-permit discussion reflects the situation on August 27, not a verified final permit decision.
The Attorney General says her August 6 appeal brief challenges the MPSC’s ex parte review and treatment of customer-cost protections. These are the appellant’s arguments; no appellate ruling was verified in this research.
Oracle’s March 30 post says vertical construction is underway and describes financing and development as on schedule. This is the developer-side company’s claim, not an independent construction or financing audit.
The MPSC’s December 2025 release describes conditional approval of DTE’s special contracts, including additional customer safeguards and a large-load tariff filing requirement. This is historical background and an official summary, not the order itself.
Direct filing dated October 31, 2025 requests expedited ex parte approval of primary-supply and energy-storage agreements with Green Chile Ventures. It documents what DTE requested, not what regulators ultimately approved.
Official case link for DTE’s special-contract proceeding, corroborated by MPSC and Attorney General releases. The page’s dynamic filing list did not load in extraction, so this is a navigation source, not a verified latest filing.